Mathematics · Time and Work · Solved question
Q14. A and B finish a job in 12 days, B and C in 15 days, and C and A in 20 days. How…
Q14. A and B finish a job in 12 days, B and C in 15 days, and C and A in 20 days. How long will A alone take?
(A) 24 days (B) 30 days (C) 36 days (D) 40 days
(A) 24 days (B) 30 days (C) 36 days (D) 40 days
Given Rates
A and B: work/day; B and C: work/day; C and A: work/day.Work Rate Principle
If a person takes days, their 1-day work is .Sum All Rates
Add all given 1-day work rates to find 's rate.Calculate Combined Rate
Simplify Sum
work/day.Find $(A+B+C)$'s Rate
work/day.Find A's Rate
Calculate A's Rate
work/day.Time for A Alone
Time taken by A alone days.
Final answer: (b) 30 days