Q14. A and B finish a job in 12 days, B and C in 15 days, and C and A in 20 days. How…

Q14. A and B finish a job in 12 days, B and C in 15 days, and C and A in 20 days. How long will A alone take?
(A) 24 days (B) 30 days (C) 36 days (D) 40 days
  1. Given Rates

    A and B: 1/121/12 work/day; B and C: 1/151/15 work/day; C and A: 1/201/20 work/day.
  2. Work Rate Principle

    If a person takes TT days, their 1-day work is 1/T1/T.
  3. Sum All Rates

    Add all given 1-day work rates to find 2(A+B+C)2(A+B+C)'s rate.
  4. Calculate Combined Rate

    2(A+B+C)=1/12+1/15+1/202(A+B+C) = 1/12 + 1/15 + 1/20
    2(A+B+C)=112+115+1202(A+B+C) = \frac{1}{12} + \frac{1}{15} + \frac{1}{20}
  5. Simplify Sum

    2(A+B+C)=(5+4+3)/60=12/60=1/52(A+B+C) = (5+4+3)/60 = 12/60 = 1/5 work/day.
    2(A+B+C)=5+4+360=1260=152(A+B+C) = \frac{5+4+3}{60} = \frac{12}{60} = \frac{1}{5}
  6. Find $(A+B+C)$'s Rate

    A+B+C=(1/5)/2=1/10A+B+C = (1/5) / 2 = 1/10 work/day.
    A+B+C=110A+B+C = \frac{1}{10}
  7. Find A's Rate

    A=(A+B+C)−(B+C)=1/10−1/15A = (A+B+C) - (B+C) = 1/10 - 1/15
    A=110−115A = \frac{1}{10} - \frac{1}{15}
  8. Calculate A's Rate

    A=(3−2)/30=1/30A = (3-2)/30 = 1/30 work/day.
    A=3−230=130A = \frac{3-2}{30} = \frac{1}{30}
  9. Time for A Alone

    Time taken by A alone =1/(1/30)=30= 1 / (1/30) = 30 days.

Final answer: (b) 30 days